Programme Length: 6 Weeks
Project Type: Strip/Demolition/foundation removal
Demolition of 4nr 3 storey structures, foundations removed. Site clearance completed for the next phase of works. Democycle Ltd acted as Sub Contractor for this project.
Overview Of Works
-
Project Management.
-
Logistics Management.
-
HSE Management.
-
Enabling works.
-
210 Hitachi 360 Excavator.
-
R400X Crusher.
-
Isolation and Draining of services.
-
Strip out of structures
-
Removal of non-notifiable and notifiable
asbestos. -
Demolition of ground slab and foundations to a
depth of 2 metres.
.
-
Reduced dig to an average depth of 1.3 Metres.
-
Supply and Install of an 875mm 1100sqm piling
mat to match the piling specification. -
Crushing of all hardcore and concrete to type 1
spec. -
Removal of all associated waste
-
Day to day issues
-
Health & safety on site
-
Retaining live service and left in situ
-
Liaising with Management team daily
-
Waste Management